Energy efficiency of the manufacturing hall
Spišská Nová VesBeneficiary:
Jochman, s.r.o.
Title of the Project :
Energy efficiency of the manufacturing hall
Operational Programme:
OP Competitiveness and Economic Growth
Measure:
2.1 Increasing energy efficiency in generation and consumption and introducing advanced technology in the energy sector
Amount of funds requested:
83 529 EUR
Completion date:
03/2015 - 08/2015
Main Activities:
- Heat cladding of fixed areas enclosing construction, roof and window replacement
- Reconstruction and modernization of the heating system and gasification
- Reconstruction and modernization of the lighting system