Increase the production efficiency of electricity and heat in the company BUKOZA ENERGO, a.s.

Hencovce

Beneficiary:

BUKOZA ENERGO, a.s.

Title of the Project :

Increase the production efficiency of electricity and heat in the company BUKOZA ENERGO, a.s.

Operational Programme:

OP Competitiveness and Economic Growth

Measure:

2.1 Increasing energy efficiency both in generation and consumption and introducing advanced technology into the energy sector

Amount of funds requested:

2 434 842 EUR

Completion date:

12/2014 - 11/2015

Main Activities:

  • Effective use of uncontrolled consumption of TG, VTO I – VTO II,
  • Modification of cooling for the condenser
  • Installation of feeding pump with frequency converter
  • Installation of new circulators